By Watertown Post Staff
Watertown’s City Council added $3,492,350.00 to its water-treatment plant engineering agreement on November 16, bringing the GHD contract to $7,458,468.00. That figure pays for engineering and related services. It is not a construction award, and it does not establish a new water rate.
Resolution 6 in the council minutes records the approved amendment. The accompanying City Manager’s memorandum describes work that includes services already provided, redesign into phases, construction administration, on-site oversight, inspections, materials testing and follow-up. Funding comes through the April 2024 bond ordinance.
What comes first
The first phase expands raw-water pumping and adds pretreatment. The work-session record and meeting summary describe plans expected in March 2027 and construction anticipated in summer 2027. Those are planning expectations, not a guarantee of a construction start.
Ozone treatment and filters belong to a possible second phase. The 2030 projection discussed for that work should not be read as a firm commitment to build it.
Why treatment changes matter
Disinfection protects drinking water from harmful organisms. As the Environmental Protection Agency explains, disinfectants can also react with material in source water to form disinfection byproducts. Federal rules address those byproducts alongside the need for effective disinfection.
The city’s water-treatment plant averages 6 million to 6.5 million gallons a day, serving Watertown and nearby communities. The engineering program concerns a system used well beyond any single street or neighborhood.
What the vote does not answer
The approved engineering total does not establish the first phase’s final construction cost, its net cost after aid, or the effect on a household water bill. Those remain important questions as the project advances. Another is what treatment results or testing would trigger the second phase.
This action is separate from the $600,000 East Reservoir engineering proposal that council put on hold at the same meeting. The two agreements should not be combined or treated as the same project.