A close-up at the Thompson Park water tower, near the underground East Reservoir in Watertown, New York. Photo by Hans Wilder.
By Watertown Post Staff
WATERTOWN, N.Y. The Watertown City Council tabled a $600,000 engineering proposal for the East Reservoir on Nov. 16 after Council Member Benjamin P. Shoen asked for more time to read the agreement. The vote postponed a decision on the contract; it did not reject the project.
The proposal from Wright-Pierce covers the first phase of a plan to reline the city’s 5-million-gallon underground drinking-water reservoir in Thompson Park. The fee would pay for planning and design, help with bidding, construction oversight and computer modeling of how water moves through the system. The city would still need to hire a contractor to do the lining work.
The reservoir dates to the late 1800s. In his memo to the council, City Manager Eric F. Wagenaar said the structure has leaked for much of its life and earlier repairs have not held up over the long term.
The larger project also calls for a new 5-million-gallon aboveground storage tank and changes to part of the transmission main, the pipe that carries water through the system. Engineering for that second phase would come back to the council as a separate contract amendment. In April 2025, the council added the broader reservoir project to its budget at an estimated maximum of $12 million. In December 2025, New York announced a $5 million award for the storage tank, reservoir lining and water-main project.
According to the Nov. 16 meeting minutes, Council Member Douglas E. Osborne Jr. seconded Shoen’s motion to table the proposal, and everyone voting supported it. The minutes do not give a date for the contract to return or a start date for the lining work.
Correction: An earlier photo was incorrectly identified as showing the East Reservoir site. It has been replaced with a photo taken at the nearby Thompson Park water tower.