By Watertown Post Staff
LERAY, N.Y. | New York regulators have approved the construction plan for rebuilding roughly 61 miles of National Grid transmission lines from Jefferson County to suburban Syracuse. The project affects six Jefferson County and six Oswego County municipalities. National Grid is aiming to start line work in spring 2027, but a separate state sign-off is still required before crews can begin that phase.
The Public Service Commission’s Nov. 20 order covers the transmission line from the Black River substation in LeRay to the Clay substation in Onondaga County. National Grid plans to replace wires and structures along the existing corridor, keep the line at 115 kilovolts and upgrade access roads. The commission says the rebuild is intended to replace aging equipment, improve reliability and give the grid more capacity to carry power from new renewable generation.
Where the line runs
According to National Grid’s route and project schedule:
- Jefferson County: The towns of LeRay, Rutland, Rodman, Worth and Lorraine, and the village of Black River.
- Oswego County: The towns of Boylston, Orwell, Albion, Parish and Hastings, and the village of Central Square. The filed Joint Proposal says work in Orwell is limited to removing existing structures.
- Onondaga County: The towns of Cicero and Clay.
What’s already happening in Rutland
There’s already work at the new Staplin Creek substation in Rutland. That part of the project was approved separately and will replace the aging Middle Road substation. In its construction update for the week of Nov. 23, National Grid lists weather-dependent drilling and foundation work at the site, with work paused Nov. 26 and 27. That schedule applies to the substation, not to the 61-mile line.
What neighbors should watch for
National Grid lists 2030 as its target for finishing the rebuild. The Post could not verify a state notice to proceed for the line work or a town-by-town start schedule as of Nov. 22. The utility says it will send notices with local work dates to neighboring landowners and municipalities before work begins. It also says additional easements may be needed in some places. For residents along the route, the next useful details will be where crews start, which roads they’ll use and whether any work affects access to individual properties.
Residents can follow state case 25-T-0184 for the construction clearance and check National Grid’s route map. The utility’s project contact number is 844-243-2592.